Sprint 37 Progress Summary
Sep 2 - Sep 15, 2009
Goals
- Outstanding BPEL items
- Subject discovery (Martha/Jon)
- Patient Correlation (Jason/Jon)
- Adapter: HIEM (possible get rid off) (Kieran)
- Adapter: Provide and register for doc registry and repository (Sai)
- Adapter: Audit log BPEL (Sai)
- Finalize "end-to-end" SAML
- Secure Entity Subject Discovery (must be done early in sprint to allow for UC to be completed) (Jon)
- HIEM (Kieran)
- Issues with patient correlation facade (Kieran)
- Review proxies (Neil)
- Dynamic reliable messaging on notification (Neil)
- Universal Client - Finalize development (Visu)
- bug fixes / polish
- has dependency on SD being complete prior to finalizing UC
- Finalize implementation of Vangent Repository (Clark)
- doc retrieve
- provide and register
- Implement Policy Engine change request (Les)
- Expand assertion class (Les)
- Extract SAML header into assertion class (Les|Vicky)
- Pass new assertion fields to the policy engine (Jason|Les)
- Extract assertion into SAML header (Les|Vicky)
- Validate that all data is included in SAML header (Les, Vicky)
- Move 2.1 fixes into 2.2 (Sai)
- Implement CPP GUI for fine-grained policy (Vicky, Visu)
- Create screen
- Include update on CCP GUI to remove dependency on OpenSSO
- Automated deployment staging env
- MySql upgrade on the test/integration/build
- Update Release 2.2 documents (create story)
- Architecture (Rim)
- Windows installs (binary+source) (Aleena, Zach)
- Solaris installs (binary) (Sri, Zach)
- Vangent plug-in (Clark)
- SOAP UI test scripts and instructions (Scott)
- Release notes (Jason, Janet) (Sprint 38)
- "joining in the nhin guidance" (VJ) (Sprint 38)
- Integrate WSDL (Sai) (Sprint 38)
- Bundling release artifacts: producing distro's for source+binary (Mark) (create story)
- Produce unix build / test on Sparc Solaris (Sri)
|
Accomplishments
Development
- Policy Engine
- Content of the Assertion class has been expanded to include information for the Authorization Decision and Evidence
- New information has been packaged into the SAML header
- Information extracted on the receiving end
- Universal Client (one-off)
- Development is complete
- Testing on DVA3 is in progress
- MySql
- MySql upgrade on the test/integration/build done
- Product Distribution
-Release distribution packaging scripts were updated
-Initial distribution of artifacts for release 2.2 were bundled
-Began validation of produced distribution
-Began work on automated deployment to staging environment
- Created and tested UNIX/Solairs Build
- Completion of Vangent Repository Integration - Some testing still remains to be done.
- Completed conversion of remaining BPEL services to Java
- Addition 2.1 Patch to resolve issues with VA
- Fixed VA bugs in 2.2 that were previously done in 2.1
- Support
- DoD VLER project
- FDA Agency Support
- IHS Agency Support
- I2 Conference Support
- NAT HIT Week
- VA Agency Support
- End To End SAML
- HIEM Implementation
CM/DM
- Documents Updated
- Windows Full Binary Installation and Configuration
- Windows Source Code Installation and Configuration
- Solaris Full Binary Installation and Configuration
- Vangent Installation and Configuration
- Updated Release 2.2 site with versions ready for QA Validation
- Supported C&A Activities
- Verified references/updated process documents as needed per this exercise
- Review CM Process Directives
Security Team
- Documents Produced:
- CONNECT Physical and Environmental and Media Protection Policy & Procedure
- CONNECT Personnel Security Policy and Procedure
- CONNECT System and Information Integrity Policy and Procedure
- Documents Revised:
- CONNECT Account Management Policy and Procedure
- CONNECT Risk Assessment and Planning Policy and Procedure
- System Development
- Solaris VM complete.
- Solaris Hardening guide 90% complete.
- Artifact Collection for ST&E
- In progress
- ST&E Preparation
- Final review and QA of documentation started
|
Summary
|
Release V2.2 (83%)
| Story Summary Details |
Planned/Assigned |
Completed |
| Stories |
42 |
35 |
| Story Points |
296 |
270 |
| Bugs Assigned |
Bugs Completed |
Bugs Remaining |
| 32 |
12 |
20 |
|
Velocity
| Sprint Velocity |
272 |
| Project Velocity |
225 |
|
Impediments
Sprint 37 Goals
- QA Validation of Release 2.2 Documents
- Edit/Format/Post Release 2.2 documents after QA Validation
- Finalize Release 2.2 site
|